2MVA transformer upgrade
ARA Electrical Services successfully executed a comprehensive project for APM Pharmaceuticals, encompassing the installation of a new 2MVA transformer kiosk and a new main switchboard.
The entire project, from design to installation, was expertly handled by ARA, which also took charge of all civil works and negotiations with the supply authority. Stringent measures were implemented to manage traffic and pedestrian flow, ensuring uninterrupted operations for the pharmaceutical plant, which operates around the clock, seven days a week.
ARA took responsibility for the design and supply of the new main switchboard, employing an innovative approach that involved repurposing the old main switchboard as a sub-board, thus optimizing project methodology.