Trevi Cellars Plant Installation

ARA Electrical Services were award the installation contract for the Trevi Cellars plant installation in Laverton.

The project included supply and installation of process equipment installed on 45 off 80,000-liter tanks, consisting of;

  • 1,300 off pneumatic valves over ASi network
  • 200 off process instruments
  • 50 off electric motors
  • CIP set
  • Automated beer cellar Filtration room
  • Installation of 400A MCC, 23 VSD’s and associated field circuits.
  • Installation of 8 remote I/O panels, including hardwired instrumentation & ASi bus networked valves and instrumentation
  • Tanker unloading system
  • Hazardous area certification and documentation