Waubra Wind Farm HV & LV

ARA were awarded the HV & LV installation contract for 68 LV & HV wind turbines. The project required the cooperation with an international consortium to successfully complete and test the installation.

Waubra Wind Farm

HV & LV installation of equipment

Energy Safe Victoria investigation and upgrades

Waubra VIC 2010

  • Supply and installation of HV & LV equipment in 68 Wind turbines
  • Investigate AS3000 non-conformance from an international supplier and rectify issues.
  • HV cables installation, termination and testing