Waubra Wind Farm HV & LV
ARA were awarded the HV & LV installation contract for 68 LV & HV wind turbines. The project required the cooperation with an international consortium to successfully complete and test the installation.
Waubra Wind Farm
HV & LV installation of equipment
Energy Safe Victoria investigation and upgrades
Waubra VIC 2010
- Supply and installation of HV & LV equipment in 68 Wind turbines
- Investigate AS3000 non-conformance from an international supplier and rectify issues.