Hazardous Area Alcohol RTD bottling plant upgrade
ARA Electrical Services were engaged to complete the relocation and modification of an Alcohol tank farm, Ready To Drink (RTD) process plant and CIP set.
The equipment was disconnected and removed from a bottling factory in South Australia. The MCC’s and control panels were delivered back to our ARA fabrication workshop to complete works on the control panel and MCC upgrades.
The project timeline was very tight, and our team was required to work very closely with the project management team and mechanical contractors on a small footprint to enable us to meet the project timelines.
ARA Electrical Services has up to 10 Electricians and apprentices on site to implement the project on schedule.
The project consisted off;